What new flooring costs in San Diego, per square foot
Replacing 1,000 sq ft of carpet with mid-grade vinyl plank in San Diego County comes to about $10,650, with an expected range of $9,375 to $13,000. That's about $10.65 per sq ft, all-in. Our samples run from $8,575 to $27,925. This is a modeled figure from our price list, last updated November 2026, not a contractor's quote. The floor itself is only part of that.
Last updated
Sample job
Carpet to mid-grade vinyl plank, 1,000 sq ft
Most likely$10,650
- Per sq ft, all-in
- $10.65
- Samples run
- $8,575 to $27,925
3 of the sample's 8 lines, marked on the drawing
- Moisture barrier over concrete slab1,000 sq ft$311
- Luxury vinyl plank — mid grade (20 mil wear layer)1,000 sq ft$5,142
- Quarter-round / shoe molding, supplied and installed220 lin ft$621
Sample jobs
Carpet to mid-grade vinyl plank, 1,000 sq ft
Most likely$10,650
Expected range$9,375 to $13,000
$10.65/sq ft, all-in
Tile to engineered wood on a slab, 1,000 sq ft
Most likely$22,900
Expected range$20,150 to $27,925
$22.90/sq ft, all-in
Sheet vinyl to porcelain, kitchen and bath, 400 sq ft
Most likely$9,725
Expected range$8,575 to $11,875
$24.31/sq ft, all-in
These are sample jobs, not quotes. Your rooms, quantities and contractor set the real price.
Prices use San Diego County labor and material costs. Homes elsewhere in the US can still get an estimate, and it will say that local costs can differ.
These samples aren't your job. HowMuch prices yours from your own answers and photos, and the line-by-line estimate of your own job, with your quantities, is free for now. Price my floors
Cost per square foot, by floor
| Floor | Installed | Whole job |
|---|---|---|
| Vinyl plank, builder grade | $5.55 | $8.88 |
| Vinyl plank, mid grade | $7.33 | $10.65 |
| Carpet and pad | $7.43 | $10.25 |
| Laminate | $7.83 | $11.18 |
| Vinyl plank, premium | $8.73 | $12.08 |
| Engineered hardwood | $12.55 | $15.95 |
| Ceramic tile | $13.18 | $16.38 |
| Porcelain tile | $16.03 | $19.23 |
| Solid hardwood | $16.45 | $19.40 |
All-in figures per square foot from our price list for a 1,000 sq ft job. The whole-job column is the first sample below, old carpet replaced in a lived-in home: on top of the floor it adds carpet removal, a moisture barrier under floating floors, trim and transitions, door undercuts, furniture moving, haul-away and the site-conditions allowance for an occupied home.
Every line of each sample
Carpet to mid-grade vinyl plank, 1,000 sq ft$10,650
| Work | Qty | Amount |
|---|---|---|
| Remove and dispose existing carpet and padAll 1,000 sq ft of carpet and pad come up. | 1,000 sq ft | $300 |
| Work | Qty | Amount |
|---|---|---|
| Moisture barrier over concrete slabA barrier goes over the slab under the floating plank. | 1,000 sq ft | $311 |
| Work | Qty | Amount |
|---|---|---|
| Luxury vinyl plank — mid grade (20 mil wear layer)Mid-grade plank clicks together over the new barrier. | 1,000 sq ft | $5,142 |
| Work | Qty | Amount |
|---|---|---|
| Quarter-round / shoe molding, supplied and installedQuarter-round along about 220 feet of existing baseboard. | 220 lin ft | $621 |
| Transition strip between flooring types or roomsFour strips where the plank meets other floors. | 4 | $255 |
| Work | Qty | Amount |
|---|---|---|
| Undercut door to clear new floor heightFour doors sit too low once the plank is down. | 4 | $129 |
| Move and replace furniture, per roomFive furnished rooms are moved and put back. | 5 rooms | $210 |
| Debris haul-away and dump fees, per truck loadOne truck load covers the old carpet and pad. | 1 load | $524 |
Line amounts are before material handling, site conditions, overhead and profit, and contingency. The rows below add those and reach the most likely figure.
| Materials (incl. handling) | $4,975 |
|---|---|
| Labor | $3,275 |
| Site conditionsoccupied home | $164 |
| Overhead & profit | $1,262 |
| Contingencyfor what turns up once work starts | $968 |
| Rounding / job minimum | $6 |
| Most likely | $10,650 |
- Materials (incl. handling)47%
- Labor & site conditions32%
- Overhead & profit12%
- Contingency9%
- Rounding / job minimum<1%
Tile to engineered wood on a slab, 1,000 sq ft$22,900
| Work | Qty | Amount |
|---|---|---|
| Demo existing tile and thinset (labor intensive)All 1,000 sq ft of tile and thinset come up. | 1,000 sq ft | $2,750 |
| Work | Qty | Amount |
|---|---|---|
| Self-leveling compound over uneven subfloorLeveling compound on about 200 sq ft of uneven slab. | 200 sq ft | $516 |
| Premium acoustic / moisture-barrier underlaymentPremium underlayment for sound and moisture over the slab. | 1,000 sq ft | $1,083 |
| Work | Qty | Amount |
|---|---|---|
| Engineered hardwood, supplied and installedEngineered hardwood across the full 1,000 sq ft. | 1,000 sq ft | $8,794 |
| Work | Qty | Amount |
|---|---|---|
| Paint-grade baseboard, 5-1/4", supplied and installedNew 5-1/4 inch baseboard along about 220 feet. | 220 lin ft | $1,221 |
| Transition strip between flooring types or roomsFour strips at doorways and other floor edges. | 4 | $255 |
| Work | Qty | Amount |
|---|---|---|
| Undercut door to clear new floor heightFour doors cut down to clear the wood floor. | 4 | $129 |
| Move and replace furniture, per roomFurniture in five rooms moves out of the way. | 5 rooms | $210 |
| Debris haul-away and dump fees, per truck loadTwo truck loads: tile and thinset weigh about 3.5 tons. | 2 loads | $1,048 |
Line amounts are before material handling, site conditions, overhead and profit, and contingency. The rows below add those and reach the most likely figure.
| Materials (incl. handling) | $9,424 |
|---|---|
| Labor | $8,018 |
| Site conditionsoccupied home, slab on grade | $641 |
| Overhead & profit | $2,713 |
| Contingencyfor what turns up once work starts | $2,080 |
| Rounding / job minimum | $24 |
| Most likely | $22,900 |
- Materials (incl. handling)41%
- Labor & site conditions38%
- Overhead & profit12%
- Contingency9%
- Rounding / job minimum<1%
Sheet vinyl to porcelain, kitchen and bath, 400 sq ft$9,725
| Work | Qty | Amount |
|---|---|---|
| Remove sheet vinyl / VCT and adhesiveSheet vinyl and adhesive come up across 400 sq ft. | 400 sq ft | $564 |
| Work | Qty | Amount |
|---|---|---|
| Self-leveling compound over uneven subfloorLeveling compound on about 60 sq ft of low spots. | 60 sq ft | $155 |
| Work | Qty | Amount |
|---|---|---|
| Porcelain tile, supplied and installed (standard layout)Porcelain tile across the kitchen and bath, 400 sq ft. | 400 sq ft | $4,692 |
| Work | Qty | Amount |
|---|---|---|
| Paint-grade baseboard, 3-1/4", supplied and installedNew 3-1/4 inch base along about 120 feet. | 120 lin ft | $601 |
| Transition strip between flooring types or roomsThree strips where tile meets the next room's floor. | 3 | $191 |
| Work | Qty | Amount |
|---|---|---|
| Pull and reset toilet, new wax ringThe toilet comes up and resets on a new wax ring. | 1 | $101 |
| Disconnect and reset appliance (fridge, washer, stove)Two kitchen appliances get disconnected and reset. | 2 | $172 |
| Debris haul-away and dump fees, per truck loadOne truck load for the vinyl and demo debris. | 1 load | $524 |
Line amounts are before material handling, site conditions, overhead and profit, and contingency. The rows below add those and reach the most likely figure.
| Materials (incl. handling) | $3,020 |
|---|---|
| Labor | $4,440 |
| Site conditionsoccupied home | $222 |
| Overhead & profit | $1,152 |
| Contingencyfor what turns up once work starts | $884 |
| Rounding / job minimum | $7 |
| Most likely | $9,725 |
- Materials (incl. handling)31%
- Labor & site conditions48%
- Overhead & profit12%
- Contingency9%
- Rounding / job minimum<1%
What moves the price
Each change is priced on this sample: Carpet to mid-grade vinyl plank, 1,000 sq ft.
| Change | Effect |
|---|---|
| Lots of small rooms and cuts | adds $500 |
| Diagonal or patterned layout | adds $825 |
| The old floor is tile, not carpet | adds $3,250 |
Where these figures come from: how we price an estimate. Have bids to weigh up? How to compare contractor bids.
What's not included
- Subfloor repairs found after demo
- Testing and removal of asbestos in old vinyl
- Stairs
- Painting the baseboard
- Moving belongings out of the home
San Diego notes
- Painting, flooring and cabinets don't need a building permit in the City of San Diego. Other cities in the county run their own rules. City of San Diego permit guide
- The exemptions don't apply to historical resources or to environmentally sensitive lands that need a development permit. San Diego Municipal Code §129.0203
- About 48% of the county's homes were built before 1980. CSLB's guidance sets no age cutoff. Material the work will disturb is tested or assumed to contain asbestos. Census ACS 2024, table B25034 CSLB asbestos guide
Common questions
What does vinyl plank cost per square foot installed?
Mid-grade vinyl plank comes to about $7.33/sq ft installed on our price list, all-in. Over old carpet in a lived-in home, with demo, barrier, trim, door undercuts, furniture moving and haul-away, the whole job comes to about $10.65/sq ft.
Why is the whole job more than the floor?
The floor is one line. Removing the old floor, preparing what's under it, trim, moving furniture and haul-away are the others, and the estimate shows each one.
Do I need a permit?
Installing floor covering is on the City of San Diego's list of work that doesn't need a building permit. Other cities in the county run their own rules.
Is old sheet vinyl a problem?
It can be. Old sheet vinyl and its adhesive can contain asbestos, so have it tested before anyone disturbs it. Testing and removal aren't in these figures.